A culvert replacement project will mean lane closures on I-91 in Fairlee starting Nov. 23, 2026, and lasting through fall 2028. (Photo courtesy Vermont Agency of Transportation)

FAIRLEE — Drivers on Interstate 91 in Fairlee can expect lane closures starting Monday, Nov. 23, as the state begins work to replace two culverts under the highway.

The northbound and southbound lanes of I-91 just south of Exit 15 will have temporary lane closures Monday through Wednesday, according to a press release from the Vermont Agency of Transportation. One lane of travel will stay open in each direction. The contractor will be off the road by noon on Wednesday, Nov. 25, for Thanksgiving, and work will resume at 7 a.m. Monday, Nov. 30.

Crews will start installing crossovers in the project area next week, according to the release. That work will take several weeks, and the full project is expected to last until fall 2028.

The project will replace two corrugated galvanized metal culverts with a single precast structure, according to a VTrans project fact sheet. The culverts carry the Lake Morey outlet and an unnamed brook under I-91 about 0.6 and 0.7 miles south of Exit 15. Both are state-owned, were built in 1971 and have been rated in serious or poor condition, according to the fact sheet.

The project is expected to cost more than $11.8 million.

A work zone speed limit of 55 mph will be in effect, and fines for speeding in the work zone will be doubled, according to the release.

Allison Rogers can be reached at arogers@vnews.com or 603-727-3220.