An architect's floor plans for the proposed police and fire facility in Norwich. (Courtesy Jay White)
An architect's floor plans for the proposed police and fire facility in Norwich. (Courtesy Jay White) Credit: —

Norwich — Selectboard members earlier this week voted to approve a new design for renovations to the fire and police facilities and made plans for a bond vote during the November elections.

The board asked Montpelier-based architect Jay White to come back with a cost estimate for the roughly 4,800-square-foot facility next month. The design would replace the current police station with a one-story combined building attached to the fire department’s existing apparatus bay off Main Street.

“I think it’s a sound design,” Selectboard Vice Chairwoman Mary Layton said at the meeting, according to a recording. “It’s simple; it’ll work with the site.”

7-12-16-COMBINED-DRAWINGS-1-(1).jpg

7-12-16-COMBINED-DRAWINGS-2-(1).jpg

Click the images above for larger versions.

Layton and others on the board praised the way White incorporated their suggestions into the design, including a request from Selectman Steve Flanders that there be space for a possible future move of the fire department’s apparatus bay.

After a 3-2 vote to accept the latest draft of the plans — Flanders and Selectman Christopher Ashley voted no, objecting to the removal of a few items — the board voted, 4-1, to approve the design and move to the site engineering stage.

Ashley was the sole dissenter.

“I, for one, think it would be important not to make a final decision over the summer,” he said before the vote. “I would like to have a public hearing, not before Sept. 1, on the design before we adopt it.”

Ashley on Thursday said he was concerned that, unlike the last time Norwich sought to renovate the emergency facilities, this process was going forward without much public input.

“August is not a good time to hold public hearings in Norwich,” he said.

In order to send out ballot information for the November elections, Town Clerk Bonnie Munday asked board members to give her the language for a bond request by Aug. 31, setting a tight deadline. The board expects to have cost estimates on Aug. 24.

Flanders, on the other hand, said he “strongly advocated” a November vote, and the rest of the board appeared to agree.

Renovations to the fire department, and especially to the police department, which has a leaky roof and substandard interview rooms, have been on the table for years.

In spring 2015, a roughly $3 million bond request failed twice, with some Selectboard members publicly refusing to support the measure based on its cost.

The board hired White in April. The Montpelier architect promised a straightforward, low-cost plan, citing the simple materials and design of a municipal facility he recently built in Royalton.

At 6,000 gross square feet, Norwich’s project would be about 21 percent larger than the Royalton building, which cost about $700,000.

The proposal is more modest than what went before voters in 2015, but in comments to the board, the police and fire chiefs indicated they could live with it.

“The revised layout of the building and parking changes satisfactorily meet the program for the Norwich Fire Department,” Fire Chief Steve Leinoff wrote in a recent letter to the Selectboard.

He added, however, that the parking arrangement for some personnel would be “less than desirable” because the department is dependent on parking spaces on land owned by the Upper Valley Grange Hall, which stands between the firehouse and Main Street.

The board’s next regularly scheduled meeting is Aug. 24.

Rob Wolfe can be reached at rwolfe@vnews.com.

Clarification

Renovations to the Norwich fire and police stations would create a facility of about 6,000 gross square feet, which is 21 percent larger than a recent public facilities project completed in Royalton by the same architect, Jay White. An earlier version of this story, as well as a prior article in early May, mischaracterized the comparative sizes of the buildings.